In June 2016 I reported on the launch of the Solastor 24-hour solar-on-demand project that was planned for Port Augusta in South Australia. At the time of the launch the plan was to have a pilot plant in operation by the end of the year. In November 2016 Solastor advised that they were likely to go ahead with the main project rather than doing the pilot first.
Today I checked in with Steve Hollis, CEO of Solastor, for an update on progress.
Brian: Your Port Augusta plans outlined in your June 2016 launch were for 1,700 collector tower modules which were expected to generate 110MW in winter and 170MW in summer. Is that still the plan?
Steve: The proposal is now to stage the project starting with a 100MW power station with 800 modules. This would do just under 50MW for 24 hours in winter and over 70MW in summer. More importantly, it will do 100MW for shorter times per day (peak hours) which is when the need is greatest.
This configuration could (would) be “cut and pasted” 5 times to give 500MW and completely replace the old to power station. Continue reading